Source : International Journal of Computer Technology and Applications, Volume 2, Issue 1, p.112-120 (2011)

Keywords : Ant colony optimization, completion time, Makespan, particle swarm optimization, planning, Scheduling, waiting time

Campus : Bengaluru

School : School of Engineering

Department : Electrical and Electronics

Year : 2011

Abstract : This paper proposes a prominent approach to solve job shop scheduling problem based on Particle Swarm Optimization (PSO) and Ant Colony Optimization (ACO). The steps to generate the solution are grouped as planning, scheduling and optimization. Initially, fuzzy logic is applied for planning and then the scheduling stage is optimized using PSO and ACO. The processing order of jobs for each machine is scheduled with an objective to find a feasible plan that minimizes the makespan, completion time and waiting time. The well known Fisher and Thompson 10x10 instance (FT10) and Adams, Balas, and Zawack 10x10 instance (ABZ10) problems are selected as the experimental benchmark problems. The results of the applied optimization techniques are compared with the computed parameters like makespan, waiting time, completion time and elapse time. The performance evaluation of optimization techniques are analysed for both benchmark problems and the PSO technique is found superior

Cite this Research Publication : P. Surekha and Sumathi, S., “PSO and ACO based approach for solving combinatorial Fuzzy Job Shop Scheduling Problem”, International Journal of Computer Technology and Applications, vol. 2, no. 1, pp. 112-120, 2011.